We built and live: a permanent frame house with an attic on the USP

A frame house with an attic is a fairly popular option for a country house in our country. Housing construction technology thus allows you to acquire your own roof on your head in the shortest possible time at an acceptable financial cost.

If you plan to save even more on construction, then you can do the actual construction work yourself. In the article we will dwell on the features of building houses on a frame basis on a summer cottage, consider the main pros and cons of such housing, consider popular projects and drawings of a frame house with an attic.

  • Roof installation
      Insulation of buildings
  • How it all began

    Introductory:

    • The plot is 6 acres, rectangular, slight slope (about 0.5 m).
    • Geodesy - a layer of black soil, 1 m thick, 30-35 m of clay, then clay with sand, aquiferous sand at a depth of 40-45 m, no high water.
    • The house is permanent, for permanent residence, one and a half floors (attic), 7.8x8.4 m, ceiling height 2.6 m.
    • The foundation is an insulated Swedish slab according to the standard scheme for light houses.
    • Construction - classic platform, thickness of external walls 150 mm, internal 150 mm, pitch of external racks 625 mm, internal 100 mm, external cladding of OSB. Wooden floor with joists, 50×200 mm, pitch 500 mm, span length 3.7 m, rafters 50×200 mm, metal tiles.
    • Insulation – stone wool, 150-200 mm, between double racks, crossbars and trims inter-crown insulation (tow).
    • The facade is imitation timber.

    Layouts.

    Design project.

    Frame.

    General form.

    Calculation.

    Construction of an attic superstructure

    So, if a new house is being built or the roof of the old one does not meet modern operating requirements, then the attic superstructure can be built, as they say, “from scratch.” What does that require. First of all, the project. You can’t just buy building materials and start construction. The attic is not a heavy structure, but this does not mean that it should be treated with less responsibility.

    It is better to order the project from professionals who will take into account the load-bearing capacity of the building walls, foundation and other building structures. And on the basis of this, they will create a project that will guarantee that an old or new house with an attic will serve faithfully for decades.

    Installation of the attic begins with laying the Mauerlat on the walls of the house. This is a beam with a section of 150x200 or 200x200 mm. It is attached to the walls using anchors that were previously installed in the reinforcing belt. The latter is poured onto the external walls of a private house. How this turns out in the end result is very clearly visible in the photo below.

    Mauerlat laid on anchors around the perimeter of a private house Source nauka-i-religia.ru

    Attic projects

    The first construction operation has been completed. It is carried out regardless of what configuration of the attic was planned by the project. As mentioned above, living quarters can be organized under any roof. For example, the photo below shows an attic under a pitched roof. It would seem that this is not a very successful example, but such projects exist, which means this confirms that it is possible to live under roofs of any configuration.

    Attic under a pitched roof Source houzz.se

    And yet there is one design that is called attic. It has a broken roof, which cannot be confused with any other.

    Classic mansard roof Source favoritst.ru

    Foundation

    The insulated Swedish stove in 2015 also just began to spread in the central regions, and in the Southern Federal District, specifically in Taganrog, adenart became a pioneer.

    adenartFORUMHOUSE Member

    According to the USP technology, the black soil had to be completely replaced, but this would not be very cost-effective. After consulting here on the forum with experienced comrades, I decided to make a pillow without removing the entire black soil layer. I removed only 30-40 cm of the root-forming layer. This decision was agreed exclusively for a light house; I would not risk a heavier one.

    Implementation according to all USHP rules.

    • The bottom of the pit was compacted and covered with geotextile with a density of 160 g/m².
    • I filled it with the first layer of crushed stone (one KAMAZ, 5-7 cm), compacted it, the subsequent layers required two unloadings, pouring, careful compaction, and with the last layer I brought the plane to the horizon.
    • I filled it with sand, after compacting the 10 cm layer was compacted to 7 cm.
    • I marked out the contours of the walls in the sand, assembled a sewer system for fitting, according to a previously drawn up diagram, dug trenches with a slope, laid pipes, backfilled them, compacted them.
    • The water supply was introduced using a PP32 pipe with a thick wall, led towards the future well at a depth of 1 m, and insulated.
    • I laid EPS with foaming of the joints, additionally fixed them with disc-shaped dowels, foaming the hole before driving in the fungus.
    • The ribs were reinforced in two rods with a diameter of 12 mm, on top of a 3x150 mm mesh for attaching the contour of the heated floor, after laying the main line, on top of the pipes there was a 5x150 mm mesh and two more reinforcement rods in the ribs, on stands.
    • For the warm floor, I immediately assembled and installed a manifold cabinet and a manifold; I specially took a larger one in order to later install a mixing unit in it, which will be needed to reheat the attic with radiators. The cabinet is located between the technical room and the bathroom, the partition will be assembled from a 50x150 mm board, between the bathroom and the kitchen there will be the same wide partition, inside of which there will be a drain riser and ventilation. The underfloor heating pipes were laid using a combined method: a snake above the external walls in increments of 15 cm and a snail inside in increments of 30 cm, secured with clamps. In the area of ​​connection to the collector, the pipes were covered with thermal insulation; the length of the circuit is about 300 m.
    • The electrical distribution panel was placed in the area of ​​the future wall between the technical room and the vestibule, and from this point the cable was routed to the internal walls of the rooms. Wiring in HDPE pipe (20 mm), two cables in one, cable VVG NG ls, in the bedroom, cross-section 3×2.5 mm, in the kitchen two such cables, in corridors and bathrooms with cross-section 3×1.5 mm, similar threw it at the VOC and the well.
    • Distribution of the water supply with the same pipe as the TP (Compipe 16×2.0 mm PE-RT/EVOH), because it was left after laying the circuits. From the entrance to the technical room there is a separate pipe for each consumer, a collector for cold water with six outlets, for hot water with four (bathtub and sink in the bathroom, kitchen sink, sink in the bathroom in the attic). I immediately laid the pipes for the attic, leaving about 5 m in reserve. Next, I pressurized the TP system before pouring.
    • I assembled the formwork from a 50x150 mm board in order to use it later on the frame, covered it with film, supports and pegs from an inch that was taken on the roof sheathing. All leads and the manifold cabinet were covered with film from EPS packaging so that they would not become clogged when pouring. The lighthouses were assembled from a 28x27 mm profile, on studs; the structure turned out to be flimsy, but when this became clear, it was too late to change it.
    • I ordered 9 m³ of concrete at the factory, with the estimated 8 m³, it took approximately 8.5 m³, concrete M300 P4, it began to grab in the middle of the pour, which is why they accelerated and it was not possible to get a perfectly flat surface, but no critical errors occurred. I didn’t do any grounding in the slab, I threw it onto the well casing pipe.

    The budget for the USHP foundation with an area of ​​65.5 m² was 236,850 rubles, approximately 3,616 rubles per 1 m². He hired assistants only for pouring, paying 5,000 rubles for the work. I spent almost 60 thousand more on tools and consumables.

    Why choose a frame house with an attic?

    The attic design adds aesthetics to the house, providing the opportunity to choose an unusual roof option due to its complexity. The presence of planes of different shapes distinguishes an attic house from single-story frame buildings.

    Also a plus is the illumination of the room - windows at an angle let in more light , opening up opportunities for variability in design.

    As a rule, it is difficult to live in such a room due to low ceilings, so the attic is used for other needs. For example, arranging a children's playroom, library or office would be perfect.

    Frame assembly

    While the slab was standing, I took care of the fence, and at the same time poured crushed stone over geotextile on the entrance area in the entrance (entrance) area from the gate and gate to the house. The fence had to be abandoned at the stage of assembling the formwork in order to complete the warm contour before winter; the first two walls were assembled and raised in almost one day, another day was spent on assembling and lifting the third.

    Assembly was complicated by the disgusting quality of the lumber - due to the curvature of the boards, the corners had to be tightened with bolts, the nails could not cope. The quick-release and screw clamps purchased ahead of time were very useful.

    Not everything went as in Larry Hohn's films; if it was level at the bottom, a lot of effort had to be made to level the top, but things worked out, the box grew. I finally leveled the walls with the help of a winch and a tow rope, cut corner jibs into the corners, the region is windy, it’s not superfluous to insure OSB for your own peace of mind. At the same time, I made an insulated blind area.

    There were no difficulties with the overlap - joists with a pitch of 488 mm, bridges (lintels) every 1220 mm, for laying OSB 1220x2440 mm, plus I added a lintel on the walls between the joists. Even without slab cladding, there is no trampoline effect with a span of 3.7 m.

    But how to tighten the OSB to the top in one, I had to rack my brains, but even then everything worked out.

    adenartFORUMHOUSE Member

    I threw 4 50x150 mm 6-meter boards from the ceiling to the ground, near the stack of OSB, fastened them with an inch at the bottom in two places and made a support so that they would not sag. I nailed another board on top, about a meter from the ground, to support the sheet. He pulled the sheet from the stack onto the boards, pushed it a little and rested it on this board, then hooked two clamps on top of the sheet and a cable to them, and pulled it up from the ceiling by the cable. The most difficult thing was to drag the first sheet, or rather, it was more scary, because I had to drag it and step back along the joists, then it was calmer on the OSB.

    I couldn’t find any rough nails on sale, so I fastened the sheathing with self-tapping screws (5 and 56 mm), with sizing using “liquid nails” from the middle price category. I twisted the screws “like in a book”, along the edge of the sheet along the edges of the walls after 10 cm, along the edges of the sheet inside the house after 15 cm, inside the sheets after 30 cm.

    I covered the first floor with OSB sheets, horizontally, with staggered seams, assembled and raised the outer walls of the attic, gables and internal supporting walls. Raising a ridge made of double boards 50x20 mm, 8.4 m long with a gable height of 4.3 m alone is another puzzle. The decision is risky, but the winners are not judged.

    adenartFORUMHOUSE Member

    And I lifted the skate, although I didn’t make the scaffolding - I lifted it with a winch as I originally wanted, in one piece. To be honest, it was scary when a 100 kg fool was hanging on a rope above you. And then I had to climb onto a wall 100 mm wide and, standing on it, having no other supports, lift the ridge with my hands and push it into the opening on the pediment. Somehow I was able to lift one side and put it in place, and lifted the other side with a winch, but then I couldn’t do much with my hands, but then the neighbor with whom we raised all the walls looked in, and together we finally defeated him !

    The quality of the lumber had an effect here too, even the boards that seemed even were bent, and the ridge tilted a little to the side, but further loading should correct it. I installed supports, the spans along the edges are 2 m, the central one is 3.5 m, there is no deflection.

    Before assembling the rafter system, I worked out all the controversial areas (strengthening the ridge, fastening the rafters, friezes, etc.) in a graphic editor, and after the approval of the collective mind, I assembled all the elements.

    I laid the membrane, filled the sheathing, laid the metal tiles in the color “moss green”.

    I covered the attic with OSB, installed energy-saving windows, as usual, having first carefully studied the theory and consulted with forum members. During installation, I was guided not only by other people’s experience and advice, but also by the current GOST for the installation seam.

    I installed a metal front door, I wanted a Finnish one, but the budget didn’t stretch it, so I had to make do with a more affordable option in the first place.

    Important points

    Having decided to use the attic space to your advantage, you will have to come to terms with the reduction in space due to sloping walls. To make a room comfortable and functional, you need to properly plan the arrangement of furniture.

    Windows in the attic are also very specific - they differ from ordinary ones in size and, most importantly, in price. Their cost is higher than classic double-glazed windows for installation in walls.

    It is important to take care of thermal insulation and choose the right roof. Without this, the attic will not be able to provide the required level of comfort for living.

    Interior decoration

    The insulation was laid flat, without trimming, although in a compressed state the thermal conductivity increases, but I didn’t waste time on trimming, the difference in the coefficients “per circle” is not so critical. The attic floor was insulated with 200 mm stone wool slabs, plus another 50 mm of glass wool underneath from the ceiling of the first floor, for sound insulation. I considered the vapor barrier purchased for the whole house to be a bit sticky and laid it in two layers in the attic, and on the first floor I used 200 micron film.

    Next, I installed the electrical panel, carried out ventilation and closed the box with a membrane.

    I taped the windows and made counter-insulation on the first floor.

    The rough cladding of the walls is standard for frame frames - gypsum plasterboard, first I did the first floor.

    I decided to make the staircase “solid”, a wooden frame with a niche, covered with plasterboard, and in the niche there was a couch and a house for a cat. The wooden base platform, stringers 60x300 mm, even in the rough version, the design really helped when I had to haul 90 sheets of gypsum board up.

    At the same time, I connected a treatment station so that water could be used.

    Before laying the tiles, I coated the base around the wet areas (bathroom, sink) with waterproofing mastic, and treated the remaining surfaces with a regular primer.

    At this stage, construction costs amounted to about 1.25 million, which included all expenses:

    • USHP – 260 thousand rubles.
    • VOC – 70 thousand rubles.
    • Well – 100 thousand rubles.
    • Tools – 70 thousand rubles.

    Condition of the house: closed circuit, ready for finishing of the first floor with floors (tiles, linoleum), interior doors, plumbing, simple kitchen and boiler room (electric boiler, boiler, etc.). The second floor is only covered with plasterboard. Both finances and time ran out, and the family decided to move. What remains to be purchased and completed:

    • Putty, fiberglass and paint - on both floors.
    • Floor coverings are on the second floor.
    • Doors to the second floor.
    • Facade.
    • Fence.

    Construction started in the early summer of 2015, almost single-handedly adenart built a one-and-a-half-story house, hired an engineer, practically finished the first floor, and moved in with his family in early March 2016.

    Determining soil type

    Each house stands on a foundation that rests on the ground. A large part of the territory of our country has clayey soils that have heaving properties - the property of increasing in volume during winter freezing.

    Heaving is typical for clayey, loamy and sandy loam soils, as well as gravelly sands and coarse rocks with a clay content of 10% or more.

    To a large extent, frost heaving depends on soil moisture. At high groundwater levels, water rises through tiny capillaries to the surface of the earth, where in winter it turns into ice.

    Surface melt and rainwater also saturate the soil with moisture. When frozen, they are capable of squeezing the foundation or part of it out of the ground. Cracks and deformations appear in structures, which leads to premature destruction of the structure.

    A frame house is much lighter than a brick or concrete one. It does not require the construction of powerful foundations resting on deep, dense layers of earth below the freezing level. But it cannot resist the forces of heaving, creating counter pressure with a large mass.

    To build a 6 by 6 frame lightweight house with your own hands and avoid its premature destruction, anti-heaving methods are used at the design, construction and operation stages:

    The design of the foundation must ensure the movement of the structure along with seasonal ground fluctuations or not react to them. In the first case it is a slab, in the second it is screw piles;

    Avoid overmoistening the underlying soil layers. This is achieved by drainage arranged under the base of the foundation, a blind area around the building, and drainage of rainwater and runoff using storm drains;

    Insulating the blind area, base and foundation will help avoid freezing of water in the adjacent layers of the earth;

    The set of measures includes horizontal and vertical waterproofing of the base of the house. Although it does not directly affect soil heaving, structures protected from moisture are better able to withstand any external influences.

    Facade, finishing touches, fence

    Work continued with cladding the façade with imitation timber, which the craftsman still preferred to “all kinds of siding.” As fasteners I used galvanized nails 2.5×5 mm, in a tenon at an angle of 45˚. Before installation, the boards were treated with colorless fire-bioprotectant, and on the façade they will already be coated with a tinted antiseptic – red-brown “Teak”.

    At the same time, interior finishing was carried out.

    adenartFORUMHOUSE Member

    On the advice of a friend, I do this:

    • I putty the joints/screws with starting putty;
    • I go through a primer with the addition of glue;
    • I glue fiberglass;
    • I putty the entire surface with finishing putty;
    • Cleaning up;
    • I paint it with white interior paint in 2-3 layers.

    ​Living room on the first floor.

    Entrance hall and corridor.

    As the heating season has shown, it is still impossible to do without radiators on the second floor, since the temperature difference is noticeable. But the stove, as intended, turned out to be an excellent heat accumulator and maintains heat after the heating system is turned off, although the boiler is set to 40˚C and is turned on only at night.

    A staircase with automatic illumination of the steps; I made the controller myself, since a ready-made one is twice as expensive. The backlight is dynamic - the room darkens, the first and last steps light up at a third of the brightness. When someone goes up or down, the remaining steps gradually light up along the way and go out behind them.

    Children's rooms are on the second floor.

    Using leftover drywall, adenart made an imitation of old brickwork in the office; everyone liked it, especially considering the “zero cost.”

    The office table is also homemade - edged board 50x150 mm, but in fact, 45x140-45, which after processing became even narrower and thinner. The frame was planed and sanded, the lid was only sanded, everything was varnished.

    We also got around to the fence - a wooden picket fence on a metal frame. Initially, a chess game was planned, but the live appearance was not impressive.

    Procurement of materials

    When we build a 6x6 frame house on a site with our own hands, we purchase and deliver materials ourselves or with the help of hired equipment. In order to bring the required quantity without excess or to avoid spending money on additional flights, the need for building materials is calculated according to the drawing.

    To build a reinforced concrete slab or strip foundation, you will need crushed stone, sand, cement, reinforcement, geotextiles, waterproofing, and polystyrene foam insulation. For drainage - perforated pipes, collector wells.

    The frame is assembled from dry planed boards 50x150 or 50x200 mm. Fastening is carried out with glue and hardware - bolts with washers and nuts, studs, self-tapping screws, staples, nails. Wooden elements are treated with antiseptics and fire retardants.

    Internal insulation is carried out with basalt wool slabs, external insulation is carried out with expanded polystyrene. For walls you will need vapor and waterproofing, sealing gaskets and mixtures.

    The rafter system is made from the same board as the frame. Roofing material - from the project or at will. Do not forget about the inch for sheathing and wind protection. A ridge profile is installed along the ridge.

    You will need materials for external and internal cladding - gypsum plasterboard, gypsum fiber board, siding, lining, filling window and door openings, stairs or steps.

    For electrical wiring, we purchase power cables, automation, and fittings. Water supply and sewerage cannot be laid without polymer pipes and shut-off valves. Ventilation in a frame house is an important condition for maintaining a favorable indoor microclimate. Its structure is treated with care. Systems of natural or forced motivation will be needed.

    Here is, perhaps, an incomplete list of what you will have to purchase in the near future.

    Conclusion

    adenart was not afraid of difficulties and lives in a house built with his own hands for his family, which is what he wishes for everyone. And its topic can be used practically as a visual aid for anyone who is just about to build or is already in the process, but is running out of energy.

    If you have doubts about your own abilities, the advice and experience of other self-builders is most welcome. If you also have a frame structure in your plans, find out how not to build the RSK its most unsuccessful version. The video is about a frame house based on a Scandinavian design, on an old foundation.

    Subscribe to our Telegram channelExclusive posts every week

    Roof covering and platform decking

    Before laying the roof, a layer of vapor barrier was laid on the rafters - a Tyvek membrane film, and on top of it - lathing. The material chosen was “Puretan” metal tiles with a slightly thicker galvanization and durable coating compared to others. During the laying of the tiles, ventilation ducts were made for the bathroom and room, as well as a stove exit.

    25mm OSB with 4-sided tongue and groove was chosen as the decking. The installation took 1 day.

    Tyvek membrane film


    installation of metal tiles finished roof metal tiles

    Preparatory stages of construction

    At each stage, you can act independently if you have confidence in your abilities. Or you can attract specialists to solve certain problems. For example, entrust the planning and design decisions to an architect or designer, and entrust obtaining an official building permit to a lawyer.

    So, we list the necessary actions:

    • building layout;
    • creation of constructive solutions;
    • choice of heating method;
    • studying the possibility of connecting to utilities (electricity, water supply, sewerage);
    • calculation of cubic capacity of building materials;
    • selection and purchase of consumables for construction;
    • approval of the project and obtaining a construction permit from regulatory authorities.

    Start of construction

    The construction of any building begins with a project. Even taking into account the simplicity of an 8 by 8 frame house, it is better to make a calculation and draw up a plan. A detailed estimate will make further work easier and cheaper.

    Next you need to choose a place for construction and clear the area. To do this, it is necessary to remove the top fertile layer of soil. After this, you can proceed to the construction of the foundation. The choice of its type should be based on data on the type of soil, freezing depth, and landscape of the site. If necessary, it is necessary to carry out or order a geological survey.

    Most often, frame houses are built on piles or strip foundations. The solution is poured as for ordinary houses - there are no special features. In the case of a strip base, a bundle of reinforcement is required, which requires wire. Concrete can be purchased mixed and ready for pouring, or you can mix it yourself using a concrete mixer on site.

    If you are building an 8 by 8 frame house with your own hands, then the easiest way will be to build a shallow strip foundation. For this foundation, it is necessary that the depth of soil freezing in your region is no more than 50 centimeters. Otherwise, it is recommended to install a slab base, which, although not cheap, is the only way out in the presence of groundwater. In controversial situations, it is recommended to seek help from professionals.

    Harness

    Before laying the beams, the tops of the piles must be coated with mastic and two layers of roofing material must be placed on them. They will serve as waterproofing. The bars themselves are treated with an antiseptic.

    The bars are installed on piles along the entire perimeter of the base. They are connected to each other in half a tree using nails 120 millimeters long. At the corners, the joints can be strengthened using metal corners secured with nails 50-60 millimeters long.

    The strapping is fixed to the base using fastening screws. The beams are placed in the heads (in special grooves) and screwed.

    It is necessary to lay a board on top of the strapping. It should cover the joints of the beams. This is where the frame racks will be mounted in the future. The board must also be treated with an antiseptic. The length of nails for fastening is 120 mm.

    Subfloor installation

    The logs are attached to the harness using metal corners. Boards are fastened to them with nails.

    Insulation is laid between the joists, and a vapor barrier film is spread over it. The last layer is plywood, which is laid on the logs around the entire perimeter.

    Frame installation

    First, the corner posts are installed. They are fixed using reinforced steel corners.

    Next comes the installation of all other racks. Corners are also suitable for this purpose. All racks are equipped with jibs. They will prevent loosening.

    Top frame beam

    In the corners, the bars must be secured using notches, in other places - with steel corners. The corners are fixed with self-tapping screws.

    To give the structure strength, diagonal slopes are installed.

    Installation of ceiling beams

    Installation is done in three ways:

    • By cutting method
    • Perforated brackets
    • Steel corners

    You can combine several methods, for example, corners and the cutting method. The beams must rest on the frame beam. Fastening is done with self-tapping screws.

    Installation of the rafter system

    Installing a roof is a labor-intensive process, so we included a description of it in a separate article, “Do-it-yourself roof of a frame house.”

    Exterior finishing

    • First, a sheathing of bars measuring 40 by 50 is installed. The fastening step is 60 centimeters. You can also use metal profiles
    • The lathing is treated with an antiseptic and fire-resistant compound
    • Next comes the installation of finishing material using a certain technology.

    A vapor barrier film is attached on top.

    Interior decoration

    There is no one to advise you here and you have the right to make it as you please.

    In this article we told you step by step how to build a frame-panel house with your own hands. We hope the information received will be useful to you.

    Photo report on the construction of a frame house with your own hands

    In this section you will find photos of the construction of a frame house, which our reader built with his own hands on weekends.

    Video of building a frame house with your own hands

    Rating
    ( 2 ratings, average 5 out of 5 )
    Did you like the article? Share with friends:
    For any suggestions regarding the site: [email protected]
    Для любых предложений по сайту: [email protected]